Highway 21 Waterline Relocation... Texas Dept. of Transportation is designing the widening of Phase 2 of Hwy. 21 East from Kurten to the Navasota River. Wickson Creek SUD is acquiring new easements for the relocation of waterlines along Hwy. 21 from Democrat Rd. to Sand Creek Rd. Well #6 - Brazos County The District has purchased property along Harris Lane for Well #6. This property is 2500 ft. west of the District’s Plant #4. This well is scheduled to produce 600 gallons per minute and should be completed in 2009. Waterline Improvements... Major waterline improvements along FM 2776 and Harris Lane are complete. Almost 2 miles of 24” and 2 miles of 18” waterline were installed at an estimated cost of a million dollars. |